Council approves $80,980 Westech pilot study tied to water treatment plant expansion
Summary
Council approved a four‑month Westech pilot study for equipment leasing as part of the water treatment plant expansion; staff said the total cost for the study is $80,980 and that the expense will be paid from the larger bond project.
Get email alerts on the Water Treatment topic
No spam. Unsubscribe anytime.
The council approved a Westech pilot proposal to lease equipment for a four‑month study related to the water treatment plant expansion. City staff said the study will inform aspects of the larger bond-funded project and clarified that the previously missing total price for the study is $80,980.
"On page 122...the total price for the 4 month study for this particular piece of equipment is $80,980," a staff member said, noting the cost will be accounted for in the larger bond project. Council moved to approve the Westech pilot proposal and authorized the city manager to execute the necessary documents; the motion passed by voice vote.
Staff brought the item back to council after a prior review in which the total price was absent from the packet, explaining the pause and subsequent clarification. The authorization allows the City to proceed with the short‑term equipment lease and study phase of the expansion work.