Change Order No.1 for Sunderland Elementary’s unit ventilators, AHU and boiler replacement increases the project total from $2,298,000 to $2,337,885.64 to cover generator replacement, tank removal and a rooftop condenser removal; the board approved the change order 4‑0.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Shashida Warner, director of planning and construction, presented Change Order No.1 for the Sunderland Elementary HVAC, AHU and boiler replacement project. Warner explained the order encompasses five requests, including replacement of a 35 kW diesel generator and removal of a 500‑gallon underground fuel oil storage tank, with several scope credits applied to offset costs.
Warner said: "In total, change order number 1 increases the previously approved project amount from $2,298,000 to $2,337,885.64." The board approved the change order by voice vote (4‑0). Warner noted the generator replacement reduces long‑term insurance and environmental risk associated with underground fuel oil storage.
Board members asked clarifying questions; there was no opposition recorded at the meeting.