Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Hughes Road CDBG project at about 80% complete; contractor and schedule updates given
Summary
Consultant Hewitt Zollars told council the Hughes Road CDBG project is roughly 80% complete ($29.5M in place) with a target completion date of Sept. 5; partial substantial completion is already being coordinated for finished areas.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Hewitt Zollars vice president Katherine Mears and project manager Chaitanya Kasuri gave the council a high-level update on the Hughes Road CDBG project, reporting the job is nearly $29.5 million complete and roughly 80% of the budgeted work is in place. "The completion date for the project is September 5," Kasuri told council, and she said the team is already discussing partial substantial completion for finished sections with WCID 1 and the Texas General Land Office (GLO).
Kasuri outlined schedule metrics (about 71% of scheduled time used, roughly six months remaining) and said the contractor meeting that day left the team hopeful the work could finish on time or slightly ahead. Council members pressed on traffic control, staging and how the remaining contingency interacts with schedule overruns; Kasuri confirmed the remaining 20% is based on the approved contract amount including any approved change orders.
