City manager outlines Hughes Road, Moore’s Addition drainage, HSIP and federal bayou work
Summary
The city manager reported Hughes Road drainage is about 73% complete, described environmental review for the Moore’s Addition drainage project, and detailed grant‑transfer and procurement work on an HSIP sidewalk/drainage project and an EWPP bayou‑clearing effort with Tetra Tech and Galveston County.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
City manager provided a multi‑part infrastructure update that touched on several projects the city is coordinating with county, state and federal partners.
Highlights included: Hughes Road drainage construction at approximately 73% completion with a proposed eastbound one‑way traffic configuration and an estimated $15,000 cost for proposed changes; the Moore’s Addition drainage improvement currently under environmental review to restore long‑standing stormwater outflow to Benson Bayou; an HSIP (Highway Safety Improvement Program) project to add sidewalks and street lights on California Avenue and 34th Street that TxDOT approved to transfer to Galveston County and convert from a state let to a local let; and an Emergency Watershed Protection Program (EWPP) partnership with Galveston County and an approved contract with Tetra Tech to prepare bond documents and manage coordination, with an estimated design and construction schedule of six months each and an estimated completion in March 2027. The manager said a $110,000 administrative‑support proposal was under consideration to handle federal compliance and procurement workload (not part of the local match).
The manager said engineers from Hewitt‑Zollars will attend the March 24 council meeting for a more detailed briefing on Hughes Road and Moore’s Addition and reiterated that county cooperation had preserved grant matches the city could not otherwise afford.