Council approves $1.3M sanitary sewer replacement contract covering 13 locations

City Council of Hurst · July 14, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council authorized a construction contract with King Solutions Services for the 2025 miscellaneous sanitary sewer replacement project at 13 locations: contract amount $1,186,859 with $113,141 contingency (total $1,300,000) and 320 calendar days for completion.

The Hurst City Council authorized the city manager to enter a construction contract with King Solutions Services for the 2025 miscellaneous sanitary sewer replacement project covering 13 locations.

Public Works staff explained the project includes a mix of construction methods—pipe bursting for some backyard locations and open-cut work for others—to minimize street impacts and costs. A council member moved to authorize a contract in the amount of $1,186,859 with a contingency of $113,141 for a total of $1,300,000 and a construction contract duration of 320 calendar days; the motion was seconded and carried.

Staff emphasized design adjustments and added locations to maximize the value of available funds. The contract covers only sanitary sewer work; staff said they will try to avoid full street closures when possible. The meeting record did not include a start date; staff will coordinate schedule and notification with affected property owners.