Board reallocates $33,767.26 in Ho-Chunk funds to cover generator project changes at county facilities
Summary
Vernon County approved reprogramming $33,767.26 in Ho-Chunk project funds to cover engineering-directed changes to generator installations at Vernon Manor and Vernon Acres, citing new electrical code requirements.
Get email alerts on the Facility Upgrade topic
No spam. Unsubscribe anytime.
The Board adopted Resolution 2026-07 on Jan. 20 to reprogram $33,767.26 of Ho-Chunk project funds to cover increased installation costs for generator projects at Vernon Manor and Vernon Acres. Highway Commissioner Hewitt presented the engineer-reviewed changes and explained that updated electrical code requirements raised installation costs.
The resolution directs use of Ho-Chunk funds held in Fund 88 to cover the increased cost. Supervisor Stanek moved the adoption and Supervisor Jacobson seconded; the motion passed on a voice vote with all present voting in favor.