Commissioners table rezoning for proposed Austin Township data center over documentation, immersion-cooling questions

Mountrail County Commissioners · September 3, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Mountrail County Commissioners on Sept. 3, 2024 tabled a request from JDE Holdings LLC to rezone roughly 3 acres in Austin Township from agricultural to industrial for a proposed data center, after Planning & Zoning asked for more documentation and information on a proposed immersion cooling system.

Chairman Trudy Ruland opened a 9:15 a.m. public hearing on a rezoning petition from JDE Holdings LLC to rezone a roughly 3-acre tract in the NE¼ of Section 21, Township 154N, Range 90W (Austin Township) from Agricultural to Industrial for a data center. Melissa Vachal, Planning & Zoning Administrator, told the board the county Planning & Zoning Commission recommended tabling the request until the applicant submits the required documentation and further information on the project.

State's Attorney Wade Enget reported the applicant submitted a substantial change to the original conditional use permit to propose an immersion cooling system; the P&Z Commission sought more data because there are no known immersion-cooled facilities in North Dakota. Commissioner Joan Hollekim moved to table the rezoning request until the Planning & Zoning Commission makes a recommendation; Commissioner Jason Rice seconded and the motion passed on a unanimous roll call vote. The board did not take further action and left the matter pending P&Z follow-up.