Engineer reports Drainage District 5 Lateral 1 tile is filled with sand; board orders report and information meeting
Summary
An engineer told the Board that the Drainage District 5 Lateral 1 tile is in poor condition and filled with sand; the Board directed the engineer to prepare and file a report and to set an informational meeting.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Collin Klingbeil of Jacobson‑Westergard updated the Palo Alto County Board that the Drainage District 5 Lateral 1 tile is in poor condition and filled with sand. Klingbeil participated by conference call and asked the Board to allow the engineering firm to prepare a formal report.
The Board agreed by consensus to direct Klingbeil to prepare and file an engineer’s report on the condition of the tile and to schedule an informational meeting for the district. Harold Christensen was noted as present for the discussion; no final repair decision or funding action was recorded at the meeting.