Board hears construction update: ceilings, ductwork and change orders at library and media center
Summary
District facilities staff walked the board through photos of ongoing work at the library and media center, noting open ceilings, soffit and beam work, chainsawing walls to access ductwork, and consultant oversights that will lead to change orders.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
Facilities staff (S6) described recent walkthrough findings at school sites, highlighting open ceilings in the library and finished ceiling work returning to the media center. "Still have a lot of ceilings left open, but there's a lot of overhead work happening," S6 said while showing photos and noting areas where soffits and an exposed beam required additional work.
S6 told the board the team had discovered some consultant omissions that will require change orders and shared that exhaust and heating systems will be replaced in restroom areas and elsewhere as the project progresses. The presenter said the district will share costs where items were consultant responsibilities and that further details will appear in next month’s update.