Road commission details bridges, resurfacing and drainage plans; Angel Road set to start mid-August
Summary
Matt from the road commission reported multiple bridge maintenance projects (Bunker, Waverly, Mulligan complete), said Angel Road is slated to start about Aug. 18 and take six to seven weeks, and described chip seal and resurfacing progress across Eaton County.
Get email alerts on the Transportation topic
No spam. Unsubscribe anytime.
Matt, from the road commission, presented a multi-topic update on county transportation projects and maintenance. He said three federal-aid bridge preventative maintenance projects (Bunker, Waverly and Mulligan) are complete and that work on Angel Road "is supposed to start about the 18th of this month and take 6 to 7 weeks," reflecting a larger schedule of repairs and detours. Matt also reported Bellevue Highway resurfacing is nearly complete and that about 65% of planned paving is finished countywide.
On more complex projects, Matt described a surcharge and reconstruction strategy for the Mower-to-Matthews segment pending permitting, and noted Nixon, Davis and Mount Hope work is underway with rolling surcharge operations where peat and poor soils require staged remediation. He summarized non-millage work with townships (50/50 cost sharing for chip seal sections) and said the road commission placed at least two county drain culvert replacements this year. Matt also announced a new director of engineering, Eric Daring, and said the commission is pursuing a plan to catch up on outstanding drain assessments and bank intercounty drain payments by October.