Board approves $47,325 contract amendment for Arrowhead wastewater project

Board of County Commissioners of Clermont County, Ohio · January 15, 2025

Summary

Clermont County approved Amendment No.1 to the Hazen & Sawyer professional services contract for the Arrowhead Wastewater Treatment Plant Elimination Project, adding $47,325 for additional design services and extending completion by 140 days; the revised contract total is $271,525.

The Clermont County Water Resources Department received board approval for Amendment No. 1 to its professional services contract with Hazen & Sawyer for Project No. 6402-60168, the Arrowhead Wastewater Treatment Plant Elimination Project in Miami Township.

The amendment adds $47,325 for additional design services, raising the contract total to $271,525, and extends the contract time by 140 calendar days, producing a revised contract duration of 448 consecutive calendar days (exclusive of County review time). The Board approved the amendment as part of the agenda item ratified during the Jan. 15 session; the action was contingent on release of the required purchase order as noted in the motion.

No project-level schedule beyond the amended contract duration was presented at the meeting and no speakers provided alternative funding sources; the record shows the item was approved by unanimous vote.

AI generated

The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.

AI can make mistakes, so if you spot one, and we will fix it for everyone.

Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.

Source