Summary

The Plant Operator told the council August averaged about 28,000 gallons per day with a peak flow of 30,000 gallons per day and reported that fence repair work at the plant is on schedule.

The Plant Operator delivered the sewage-plant monthly update, reporting August average flow of approximately 28,000 gallons per day and a peak high flow of 30,000 gallons per day. The operator told the council fence repair work at the plant is on schedule.

No operational alarms or emergency repairs were recorded in the minutes and the Plant Operator provided no additional budgetary details at the meeting.