Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Sewage Plant topic
No spam. Unsubscribe anytime.
Sewage plant reports August average flow near 28,000 gallons per day; fence repairs on schedule
Connoquenessing Borough Council · September 2, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.
Summary
The Plant Operator told the council August averaged about 28,000 gallons per day with a peak flow of 30,000 gallons per day and reported that fence repair work at the plant is on schedule.
Get email alerts on the Sewage Plant topic
No spam. Unsubscribe anytime.
The Plant Operator delivered the sewage-plant monthly update, reporting August average flow of approximately 28,000 gallons per day and a peak high flow of 30,000 gallons per day. The operator told the council fence repair work at the plant is on schedule.
No operational alarms or emergency repairs were recorded in the minutes and the Plant Operator provided no additional budgetary details at the meeting.
