Committee approves 14-foot sign as change order for new highway facility
Summary
The Highway Committee approved a 14-foot sign as part of change orders for the county highway facility after Highway Commissioner Derek Mashuda reported missing bid items in the original packets; the motion carried with no negative votes.
Get email alerts on the Facility Construction topic
No spam. Unsubscribe anytime.
During a facility update on June 10, Highway Commissioner Derek Mashuda told the committee that several bid items were missing from bid packets for the new highway facility, resulting in change orders. Mashuda asked the committee for a recommendation on sign size, citing visibility concerns with the originally planned sign. The committee approved a 14-foot sign as part of the change orders by motion (mover: Bob Schweder; seconder: Charlie Wielgosh); the motion carried with no negative vote as recorded in the minutes.
Mashuda also updated the committee on other change orders and the general progress of the building. The transcript notes the construction progress and multiple change-order items but does not list dollar amounts or detailed line-item costs for the change orders in the meeting record.