Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Library Building topic
No spam. Unsubscribe anytime.
Select Board approves library change orders after hearing contractor issues with subfloor and septic
Summary
Library building committee has approved change orders to address unexpected subfloor replacement, plumbing/septic and structural header work; board recorded a motion and voted to approve moving the finance order forward (amount read aloud during the meeting).
Get email alerts on the Library Building topic
No spam. Unsubscribe anytime.
The board discussed a package of change orders related to the Middletown Springs library renovation and heard a detailed account of unanticipated construction work. A contractor or library representative described tearing out existing carpet because the subfloor was unsuitable, replacing plumbing under the slab, and adding a new header to support a mezzanine area; these changes were presented as necessary to preserve warranties and ensure structural safety.
After the scope was explained, the board reviewed a finance order to record the change and moved to approve it. The chair asked for discussion, a motion was made and seconded, and members voted in the affirmative to approve the order to move the change orders forward for payment processing.

