Contractors report 97% pipe completion; board approves pay apps totaling ~$699,938
Summary
Staff reported Hudson's Sogony phase 1 is roughly 97% complete for pipe and grinder installations, and the board approved pay application #12 for $98,126.05 and pay application #10 for $601,812.71.
Get email alerts on the Construction Payments topic
No spam. Unsubscribe anytime.
Dan reported construction progress on Hudson's Sogony phase 1, saying "we are at 97% complete on pipe on the project" and that about 97% of grinders were installed with two remaining that were not yet hooked up. Dan introduced two pay applications for board execution: Contract Day pay app #12 for $98,126.05 and Contract B pay app #10 for $601,812.71. After review of quantities, the board moved, seconded and approved both payments by voice vote.
Dan also described remaining work including jack and bore crossings and final punch‑list items; the inspector had prepared a pre‑punch list to be addressed during remaining restoration work. Board members asked for bite‑sized detail in the engineering meeting and confirmed that two grinders remain to be tied into a force main once pressure testing is complete.