Porter PWA approves change order to relocate Muskogee master meter on Highway 16
Summary
The Board approved change order #1 from Jerry’s Excavation, Inc. to move the Muskogee master meter on Highway 16 from the south side of the road to the north side; the motion carried unanimously.
Get email alerts on the Water Infrastructure topic
No spam. Unsubscribe anytime.
The Porter Public Works Authority approved change order #1 from Jerry’s Excavation, Inc. for the water transmission line project at its May 8 meeting. The change order directs relocation of the Muskogee master meter on Highway 16 from the south side of the road to the north side.
Norma Meyer moved to approve the change order; the minutes record the motion and a second and show a unanimous vote in favor. The change order was reviewed by the Board during the meeting as part of agenda item 8(a).
The minutes identify Jerry’s Excavation, Inc. as the contractor; the document does not specify a dollar amount or revised schedule for the change order.