Contractor reports trenching done, awaits concrete to finish Grindstone tower work
Summary
Contractor Kenny reported foundations and raceway between towers are complete and trenching is done; final backfilling waits on a synkosha concrete delivery Peyton has ordered. Verizon is moving services to the new Lamoille tower and is awaiting site drawings.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Contractor Kenny told the board that foundation work and the raceway between the two towers are complete and that trenching and conduit placement were finished, with backfilling pending a synkosha concrete pour. “All of it... that's been up to date,” Kenny said, and he added that the remaining hold-up was the concrete delivery from Peyton.
Kenny also said Verizon is coordinating a move to the new Lamoille tower and is waiting on site drawings; AT&T had been offered alternative locations for its generator and had not yet confirmed a choice. The board discussed access and weather concerns — work is possible by 4WD so long as rain or snow does not impede crews — and expects the next set of drawings soon to advance the site work.