Fireflies details make-ready work, expects 1,405 passings and ~750 potential connections in new zone

Campbell County Board of Supervisors · February 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Fireflies representatives told the board they split a new service zone into two, expect about 1,405 passings and roughly 750 potential customer connections, and described remaining make-ready and pole-attachment work with APCO Electric.

A Fireflies representative (speaker 7) outlined the company's sequencing for construction and make-ready work in two new service zones in Campbell County. "We'll end up with, 1,400 and, 5 passings in this new area and expect to connect about 7 50 folks," the representative said, describing how the zone split will support more accurate customer communications.

The speaker detailed make-ready coordination with APCO Electric, noting three remaining 50-pole proposals and an expectation the largest make-ready packages will take 130'200 crew hours (approximately 3.5 to 5 weeks each). Fireflies said they expect some South Side work to lag by a month or six weeks because of late attachment agreements, but they plan parallel underground work to keep schedules moving.