River Street contractor says construction nearing first service turn-ups after weather delays

Campbell County Board of Supervisors · February 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Rob Taylor of River Street told the board the contractor has started multiple cabinet builds and that construction shows progress despite weather setbacks; boring is about 57,000 feet and the team is close to turning up the first ~109 locations.

Rob Taylor of River Street reported to the board that construction continues across multiple cabinet areas and that several VDOT and railroad permits have been submitted or received. "Construction has been about 99% complete for the boring, which is about 57,000 feet," Taylor said, and the team has completed roughly 53,000 feet of plowing.

Taylor said the project is under construction at about 269 locations and that weather caused roughly a three-week stoppage that delayed the planned turn-up of approximately 109 initial service locations. He described next steps: completing final splicing, preparing customer mailings when those locations are ready, and moving crews into successive cabinet areas as permits and contractor assignments are finalized.