Council approves $169,033.99 change order for fitness center Phase 2; project 35% complete

La Porte City Council · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized Change Order 1 (three combined CPRs) totaling $169,033.99 for Phase 2 of the Recreation & Fitness Center renovation, covering pool repairs, AV/network upgrades, and miscellaneous construction adjustments; substantial completion expected June 2026.

Council approved Change Order 1 for Phase 2 of the Recreation & Fitness Center renovation, adding $169,033.99 to the project contract with Construction Masters of Houston.

Public Works staff explained Change Order 1 comprises three change‑proposal requests: CPR1 ($26,001.87) for minor construction changes, CPR2 ($98,743.14) to address pool area drain and piping replacement uncovered during demolition, and CPR3 ($44,000.93) for AV and network equipment changes with some credits applied. The total construction budget is $3,042,297; the current contract amount is $2,589,000 and $453,002.97 remained in contingency. Staff said the project is 35% complete and substantial completion is anticipated in June 2026. Council approved the change order by voice vote.