Board deducts $34,450 from owner contingency on Rattlesnake wastewater GMP
Summary
Commissioners approved Contract Change Order #8 for the Rattlesnake Wastewater Treatment Plant, deducting $34,450 from the project owner contingency while leaving the guaranteed maximum price unchanged at $18,289,538.00.
Get email alerts on the Rattlesnake Wastewater topic
No spam. Unsubscribe anytime.
The Fayette County commissioners approved Contract Change Order #8 for the Rattlesnake Wastewater Treatment Plant on January 27. The board accepted a request from Peterson Construction to deduct $34,450 from the embedded owner contingency of the project's Guaranteed Maximum Price (GMP); the motion specifies there is no change to the contract amount of $18,289,538.00.
The change order was approved by roll call after a motion by Commissioner Tony Anderson and a second from Commissioner James D. Garland; Donald L. Fleak was recorded as absent. County meeting minutes indicate the deduction reduces owner-side contingency accounting for the project but does not alter the contractor's GMP figure reported at the meeting.