Board deducts $34,450 from owner contingency on Rattlesnake wastewater GMP

Board of Fayette County Commissioners · January 27, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Commissioners approved Contract Change Order #8 for the Rattlesnake Wastewater Treatment Plant, deducting $34,450 from the project owner contingency while leaving the guaranteed maximum price unchanged at $18,289,538.00.

The Fayette County commissioners approved Contract Change Order #8 for the Rattlesnake Wastewater Treatment Plant on January 27. The board accepted a request from Peterson Construction to deduct $34,450 from the embedded owner contingency of the project's Guaranteed Maximum Price (GMP); the motion specifies there is no change to the contract amount of $18,289,538.00.

The change order was approved by roll call after a motion by Commissioner Tony Anderson and a second from Commissioner James D. Garland; Donald L. Fleak was recorded as absent. County meeting minutes indicate the deduction reduces owner-side contingency accounting for the project but does not alter the contractor's GMP figure reported at the meeting.