East Bank Boulevard acquisition, AECOM scope shifts and utility plans outlined
Summary
East Bank Development Authority staff told the committee they are holding about $60,000,000 to complete right-of-way acquisitions, described AECOM scope changes after new development plans, and detailed coordination with TDOT, Metro Water Services and NES on utilities for the Central Waterfront redevelopment.
Get email alerts on the Planning topic
No spam. Unsubscribe anytime.
Ben York, CEO of the East Bank Development Authority, told the committee that East Bank is holding roughly $60,000,000 across CSP cycles to complete right-of-way purchases tied to East Bank Boulevard work that the council originally approved in 2023. York said stakeholder input and private development proposals changed the project footprint and required an amended AECOM scope.