Change order for Frank Staton Boulevard adds $43,297 and 10 days, jurors approve

Bossier Parish Police Jury · April 15, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Police Jury approved Change Order No. 1 for the Frank Staton Boulevard Extension (Project No. 2025-100), increasing the contract by $43,297.53 and adding 10 days due to additional work and soft soil mitigation; a resolution authorizing execution of documents was adopted unanimously.

Assistant Parish Engineer Matt Redmon reported that Change Order No. 1 for Project No. 2025-100 (Frank Staton Boulevard Extension) results in a $43,297.53 increase and an additional 10 days to the total contract time because soft and unsuitable soil required undercut and replacement and additional work under the construction stipulation agreement. Redmon recommended approval so the contractor can be reimbursed and the work included in the contract.

The jury approved the change order on a motion by Jimmy Cochran, seconded by Glenn Benton. A resolution was offered and adopted authorizing the Parish Administrator and/or Parish President to execute all documents associated with the change order; the vote was unanimous.