Parish says $1.2 million sewer plant repairs need additional work to meet DEQ standards

Bossier Parish Police Jury Health, Water Sanitation & Sewer District Committee · April 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Dr. Ken Ward told jurors Project No. 2024-121 (CSR and headworks repairs) was removed from ARPA funding due to timing, is now charged to the 305 Capital Projects account, and is estimated at $1,200,000 with about $700,000 remaining to reach DEQ compliance.

Parish Administrator Dr. Ken Ward described Project No. 2024-121 — the CSR and headworks repairs at the Consolidated Waterworks/Sewerage District No. 1 treatment plant — saying the project was initially proposed for ARPA funding in 2024 but missed federal timing requirements. He said the parish is funding the work through its 305 Capital Projects account and that the consolidated district will repay the total cost upon project completion.

Dr. Ward estimated the project’s total cost at approximately $1,200,000, with roughly $700,000 remaining to bring the plant into full compliance with Department of Environmental Quality (DEQ) requirements. He said a recent DEQ inspection identified additional items needing repair and that staff will explore grants and low-interest loan options for a follow-up project. Juror Tom Salzer asked whether rusted parts are steel; Dr. Ward said galvanized steel appears to have been used and that the parish will consider stainless-steel alternatives for replacement.