Land Bank reports work at Froebel (417 Jackson) and contracts signed for Shaw Walker (920 Washington)
Summary
The board was told that work at 417 Jackson Ave (Froebel) is progressing on roof and drains and the project received an additional $100,000; contracts have been signed for roof and concrete work at 920 Washington Ave (Shaw Walker).
Get email alerts on the Project Development topic
No spam. Unsubscribe anytime.
The Land Bank reported construction progress and contract awards for several Round 4 projects. Staff said the Froebel project at 417 Jackson Ave is progressing on roof and drain work and was awarded an additional $100,000 in grant funding. The Executive Committee had earlier approved the first draw for the project.
For 920 Washington Ave (Shaw Walker) the minutes record signed contracts with J Stevens for roof systems (three buildings) and RAM Concrete for concrete repair and restoration. The board noted a change order was approved for 510 Ada and that other Round 4 work is progressing. No contested votes or dissent were recorded in the minutes.
Staff did not provide precise contract amounts in the minutes; the board will receive further updates as projects move toward completion.