Commissioners approve $8.6M in water projects including $6.47M Bonaire elevated tank

Houston County Board of Commissioners · November 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board awarded contracts for multiple water projects: Dunbar Water Treatment Facility remodel ($49,737.30), Water System Improvements to serve Cemex ($2,076,756.89), and a 1.5-million-gallon Bonaire composite elevated tank ($6,470,000); ARPA and capital funds will pay for major items.

During the Nov. 5 meeting, the Houston County Board of Commissioners approved a package of water infrastructure projects and a related contract change order.

The Board awarded Plumbline Construction LLC a $49,737.30 contract for a remodel of the Dunbar Water Treatment Facility (to be paid from Water Capital Funds). It approved the low bid from John R. Walker Inc., $2,076,756.89, for Water System Improvements to serve Cemex (ARPA-funded). For Bonaire, the Board approved a best-value bid of $6,470,000 from Landmark Structures to construct a 1.5-million-gallon composite elevated water tank; Commissioners noted the county switched from a pedestal to a composite design and that ARPA and Capital Funds will fund the project.

The Board also approved Change Order #1 on the Waterline Extension to serve Scott Road, deducting $18,840.25 and lowering the contract from $595,426.05 to $576,585.80 to reflect actual quantities installed. All motions were approved unanimously. Chairman Perdue said the county was "excited at being able to afford a larger tank than initially thought possible" using designated ARPA funds.