Council weighs removing diving well, adding splash pad as part of Riverview options
Summary
Councilors and staff discussed options including removing the 14‑foot diving well and installing a separate splash pad filtration system so features can operate independently; CIP timing for projects was discussed with FY 2028–29 potential construction years.
Get email alerts on the Facility Planning topic
No spam. Unsubscribe anytime.
During discussion of the pool assessment, councilors and staff explored design options that could reduce long‑term costs and increase accessibility, including removing the deep diving well and creating a separate kiddie area or splash pad.
One council member noted the diving well had been built to serve a diving team and suggested lowering that area to create an ADA‑accessible kiddie area. "The kiddie pool has always been a problem. It's not ADA accessible to start with," the council member said while urging planners to consider CIP timing and broader redesigns. Staff and some council members also recommended separating filtration so a splash pad could operate independently from the main pool, allowing seasonal use even if the main pool is offline.
Members discussed treating the initial engineering steps as early CIP work so options and costs would be known in time for FY 2028–29 construction windows rather than delaying the project several years.