Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Thickened sludge pumps and skimmings tank drawings approved; equipment onsite, delivery pending
Summary
Two west thickened primary sludge pumps are set to start April 27, 2026; the final drawing set for Building #8 skimmings decant tank was approved and provided to the manufacturer, and all primary skimmings equipment is onsite.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Staff reported progress on dryer and skimmings projects, with staged pump startups and approved drawings for a decant tank.
Startup of the two west thickened primary sludge pumps was scheduled for April 27, 2026; installation on the two east pumps will commence after the west units are online. All primary skimmings equipment is onsite and work on skimmings systems will begin following completion of thickened primary sludge construction. The final drawing set for Building #8 skimmings decant tank has been approved and provided to the tank manufacturer, which the District said is expected to provide a delivery date in the near future.
Commissioners received these construction and procurement updates; no formal actions were taken at this meeting.
