Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Construction topic

No spam. Unsubscribe anytime.

Courthouse work continues under $7M+ change order; community-center repairs and inspections remain weather-dependent

Taos County Commission · February 4, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

County construction updates included a signed change order exceeding $7 million on the historic courthouse, continued weather-related delays, additional change-order pricing for damaged plaster, vandalism repairs at a detox center, and outstanding permit/inspection work at community facilities that may delay occupancy.

A county construction manager updated commissioners on multiple capital projects, including the historic county courthouse and several community facilities.

Richard Sanchez reported that a change order exceeding $7 million has enabled several crews to work on the courthouse; he described foundation and retaining-wall pours, elevator openings and temporary roofing to keep the structure dry during work. Sanchez said weather has delayed some pours and described the need for an additional price to remove damaged plaster in a kitchen area for safety reasons. He also described vandalism and glass damage at a detox center and the need to complete additional scope items before occupancy in some community facilities.

Commissioners raised questions about contractor meetings, the fire-suppression system, and drawdown timing for federal grants. Staff cautioned that final occupancy can be delayed by fire-marshal inspection backlogs and by weather-dependent site work even if construction completes on schedule.