Board approves GMP amendment for Adel EMS Station, weighs alternates
Summary
Supervisors approved GMP Amendment #2 for the Adel EMS Station, accepting a $6,134,593 maximum price (about $602.49/sq ft). The board discussed construction alternates, prioritized Alternates 1—3, and asked staff to revisit alternates at the August 4 meeting.
Get email alerts on the Ems topic
No spam. Unsubscribe anytime.
The Dallas County Board of Supervisors approved a guaranteed maximum price (GMP) amendment for the Adel EMS Station on July 21 and authorized the chair to sign GMP Amendment #2. Farnsworth Group's Kristofer Orth presented a project estimate showing a current maximum price of $6,134,593, or roughly $602.49 per square foot, which he described as consistent with market conditions.
Discussion centered on project alternates, including a proposed aluminum pergola with wood privacy slats (Alternate #3) versus lower-cost patio umbrellas. Orth said the pergola would be expected to last 25 to 35 years and recommended prioritizing Alternates 1—3, while noting Alternates 4 and 5 were less critical. Operations Director Rob Tietz told the board the project budget had capacity to include alternates. The board agreed to revisit alternates at its August 4 meeting.