KDOT plans June–July 2026 start for Highway 56 bridge replacement near Garfield; closure expected 140–150 days

Pawnee County Board of Commissioners · February 2, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Road and Bridge staff reported KDOT's planned June–July 2026 start for a Highway 56 bridge replacement with an expected 140–150 day closure; county and City of Larned will coordinate detour routes and utility relocations may be required, pending environmental study timing.

Road and Bridge Director Kurt Demel reported that the Kansas Department of Transportation has set a start window of June or July 2026 for a Highway 56 bridge replacement project heading to Garfield and that the projected closure will last approximately 140 to 150 days.

Demel said KDOT will meet with Pawnee County and the City of Larned to discuss detour routes and that relocations of a phone line and Mid-West Energy facilities may be required. He cautioned the start date could shift depending on the results of environmental reviews. "KDOT has a start date of June or July of 2026, and the bridge will be closed for approximately 140 to 150 days," Demel said.

No formal county action was recorded; staff will participate in KDOT coordination and detour planning with city officials.