Planning loan filed to design Deyo mobile home park water connection, construction eyed for summer
Summary
Board members heard that a planning loan application has been submitted to design a connection for the Deyo mobile home park; the Bond Bank review is expected in early March and construction could occur summer or early fall if approvals follow.
Get email alerts on the Infrastructure Residential Connection topic
No spam. Unsubscribe anytime.
Doug Kilburn, a member of the Board of Water Commissioners, reported progress on connecting the Deyo mobile home park to town water and said the project is moving from preliminary discussion to design review.
Chrissie Haskins, the Town Water Engineer, told the board that “the planning loan application has been submitted for the design” and that she hoped the Bond Bank would review the application in early March. Haskins said the Vermont Economic Development Authority (VEDA) will communicate directly with the property owner to complete required paperwork. Board members discussed the scope of work covered by the loan and the sequence of approvals; construction timing was discussed as likely summer or early fall if approvals and funding proceed.
The board did not take formal action on this item; members asked staff to track the Bond Bank and VEDA steps and return with a timeline at a future meeting.