Facilities‑bond projects on track; Mullins PreK–8 walkthrough set for Aug. 6
Summary
District staff reported progress on multiple facilities‑bond projects, including gym floor and electrical upgrades with August completion targets, and said the new Mullins PreK–8 school is on target with a first walkthrough Aug. 6 and orientation Aug. 20; staff said the overall bond program is $237,602.88 under budget.
Get email alerts on the Construction topic
No spam. Unsubscribe anytime.
District facilities staff gave a detailed progress report on multiple bond-funded projects, saying several items are near substantial completion and that the new Mullins PreK–8 school is on schedule. Substantial completion dates cited: Pineville Middle gym floor Aug. 17 and electrical work at Berlin and Pima Middle Aug. 14. For Mullins, the first substantial-completion walkthrough is scheduled for Aug. 6, furniture delivery the week of Aug. 10 and a building orientation on Aug. 20; staff said the district expects to open while finishing remaining punch-list items in limited areas.
Staff highlighted construction coordination challenges — weather-related masonry delays at the Westside practice facility and a learning curve installing DBU classroom HVAC units for which Nitro (the installer) added personnel. The presentation included staffing and contractor names involved in management (McKinley, SQP, Nitro) and stated that the overall facilities bond budget was approximately $237,602.88 under budget after accounting for the awarded wastewater plant contract.