Council approves second GO bond tranche to fund STAR Center project
Summary
The council authorized a second general‑obligation bond tranche intended to complete funding for the STAR Center project; staff and the town’s financial adviser reported oversubscribed bonds, a TIC of about 5.46% for the taxable GO series, and a double‑A credit affirmation.
Get email alerts on the Public Finance topic
No spam. Unsubscribe anytime.
The Northlake Town Council approved an ordinance authorizing the issuance and sale of the town’s general obligation taxable bonds series 2025 to fund the STAR Center project, authorizing a principal amount stated in the ordinance as $22,280,000.
Staff reviewed the project financing: voters approved a $45,000,000 authorization for the STAR Center on Nov. 7, 2023; a 2024 issuance produced $22,710,000 (with $22,500,000 going to the project fund and $210,000 used for issuance costs), and staff briefed council that the second tranche being considered would provide roughly the remainder of the project fund (staff referred to a second tranche near $22,290,000 that, together with the first tranche, would produce about $44,790,000 available for the project). Financial advisor Marty Hsu said the taxable GO bonds sold through a negotiated sale and were oversubscribed, reporting a final true interest cost of 5.46% and that both S&P and Fitch affirmed a double‑A level credit rating for the town.
Councilor Holmes moved to approve the ordinance; the motion passed unanimously. The ordinance authorizes the town to issue the second tranche and anticipates delivery of funds on or about March 27, subject to closing.