District reports power-surge damage repair, 3rd-floor renovation and gym-floor bids

Yamhill Carlton School District Board of Directors · January 9, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The district's facilities director reported repairs from a recent power surge (battery backups, server and emergency lighting), completion of a high-school third-floor renovation with new LVP flooring, and upcoming bids for gym-floor and exterior lighting repairs.

Ian, the district facilities director (speaker S4), told the board the facilities team is finishing repairs caused by a power surge and is completing several building projects.

"We're just finishing up with damages caused by power surge," S4 said, listing battery backups, fire-system and server work and emergency lighting as part of the response. S4 said the high school's third floor renovation is nearly complete — "we got the old carpet out, and we have new laminate LVP in there" — and that asbestos abatement is planned for other floors. He also said the district will solicit bids for gym-floor repairs and exterior lighting on the high school's southwest corner.

Board members asked about timelines and asbestos locations; S4 said the third floor did not have original asbestos but other floors do and that the repairs and remaining projects are expected to wrap by spring.