Board approves PBM task orders for Phase I environmental assessments; staff takes bids and proposals under advisement
Summary
Staff requested and the board approved task orders with PBM Consultants for Phase I environmental site assessments at two properties (each not to exceed $6,000) and took several procurement items under advisement, including bids for the Duncan Park Golf Clubhouse and proposals for a Fine Avenue drainage project.
Get email alerts on the Environment topic
No spam. Unsubscribe anytime.
City staff asked the board to approve task order number 5 and number 6 with PBM Consultants for Phase I environmental site assessments at former commercial sites; each task order was described as a Phase I ESA not to exceed $6,000. The board voted to approve the task orders.
Staff also summarized procurement steps for the Duncan Park Golf Clubhouse renovation (bid opening scheduled) and reported proposals received this morning for the Fine Avenue drainage project (EPA FY26 community grant). The board moved to take the procurement proposals under advisement and to allow the appointed committee to review and recommend award decisions.