Selectboard approves $15,614.70 Town Hall front-door replacement contract
Summary
Quarry Hill Construction was hired to replace the Town Hall front doors and framing under a $15,614.70 contract (Option 2), replacing the frame, jamb and trim as recommended.
Get email alerts on the Facilities topic
No spam. Unsubscribe anytime.
The Selectboard reviewed two quotes from Quarry Hill Construction for the Town Hall front doors. Option 1 would reuse the existing frame and threshold and install new 2-inch-thick doors for $13,433.15. Option 2 called for removing and replacing the frame, jamb, threshold and associated trim and siding work with new 2-inch-thick doors and related framework at a total cost of $15,614.70.
John Roleau moved to hire Quarry Hill Construction for Option 2 at $15,614.70; the motion was seconded by Marie Jewett and approved 5–0. The board did not record extended discussion on alternatives or financing in the minutes; the contract amount will appear in vendor records.