Remote inspection raises questions about reservoir coating; council weighs inspection and repair costs

Mabton City Council · November 26, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Video from a remote vehicle showed possible paint flaking and small corrosion spots inside Reservoir 1; staff outlined options ranging from a $5,000 ROV follow‑up to diver inspections (~$5k–$10k) and full draining/coating projects (potentially $250,000–$1.5M depending on scope).

Staff presented results from a remote inspection of Reservoir 1 and said video captured flakes on the floor and pinholes or small corrosion spots on internal ladders and fittings. The presenter explained the floor imagery was ambiguous: "Best case scenario is that was a paint flaking off and it was some other... manganese in your system is precipitated"; "Worst case scenario is that was a paint flaking off and then the metal underneath is as is trusted," he said, and added the video alone cannot resolve which is correct.

The presenter outlined three response options: (1) drain the tank and perform a full interior inspection and recoating (most expensive, complex and time‑consuming); (2) use divers to inspect the floor and coating more closely (mid cost, historically $5k–$10k); or (3) perform a focused ROV/ROV follow‑up to get clearer video (least expensive, ~ $5,000). He warned that a full interior recoating could range from roughly $250,000 to as much as $1.5 million depending on scale and scope. Council asked whether the tank had been drained before; staff said it has not been drained since it went online around 2018 and suggested reviewing past inspection reports for context.

Council directed staff to get estimates and to consider a diver inspection or ROV follow-up as near‑term steps while exploring funding options, including whether county ARPA funds could be repurposed to help pay for any urgent work.