Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Infrastructure topic

No spam. Unsubscribe anytime.

Staff reports bidding and construction updates: pump station, multiuse path, Gateway Park parking, Adams Avenue work

Sisters Public Works Advisory Board · May 13, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff updated the board on active bids and construction: Rope Street pump station and Elm Street multiuse path are out to bid, Camp Polk pre‑construction is set, Gateway Park added 23 parking spaces (including 3 ADA and conduit for six EV chargers), and Adams Avenue construction aims for a Sept. 30 completion.

Staff provided a round‑up of capital projects and procurement status during the meeting. Paul said Rope Street pump station improvements are out to bid with submissions due in early June, the Edgington Transmission/Elm Street multi‑use path is also out to bid, and Camp Polk Multiuse Path has a pre‑construction meeting scheduled.

Paul highlighted Gateway Park parking improvements: 23 new spots plus three ADA spots were completed on West Cascades, and the work included conduit and vaults to support six future EV chargers. On Adams Avenue, staff described extensive underground work—stormwater, utilities and new streetlight infrastructure—and set a final completion date of "September 30." Paul said the Westside Pump Station wet well was sealed and tested and pumping equipment installation is scheduled in the coming weeks.

These updates set near‑term expectations for contractors and property owners and establish sequencing for sidewalk, streetscape and utility work across town.