Council approves no‑cost change order to CDBG waterline project to add 300 feet of 8‑inch line and relocate hydrant
Summary
Council approved change order No. 6 for the CDBG waterline project: a no‑cost modification that adds 300 feet of 8‑inch water line on SW 3rd and relocates a hydrant, offset by specification changes in asphalt replacement to keep costs neutral.
Get email alerts on the CDBG topic
No spam. Unsubscribe anytime.
Council approved Change Order No. 6 on the CDBG waterline project, a no‑cost change that adds 300 feet of 8‑inch water main on Southwest 3rd Street and relocates a hydrant to reduce duplication of hydrants on private property. The change was offset by a revision in the asphalt replacement specification for Main Street parking that reduced overall field quantities and kept the change order cost neutral.
"This is a no cost change order," staff stated, explaining that the additional pipe and hydrant relocation were balanced by changes to pavement specifications. The modification was described as a practical solution to cover utility coverage and avoid two hydrants on one private property while providing hydrants where they were missing.
Council moved and approved the change order; staff said the modification helps finalize project work ahead of Maydays and will be memorialized in project records for final acceptance.