Price Barbershop project moves forward after structural issue flagged
Summary
Economic development director Nicole Dozier said the architectural and structural contract is executed, a pre-construction site walk occurred, and the design team is evaluating stabilization options after detecting significant vertical cracking in a separation wall.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
The board received an update on the Price Barbershop rehabilitation project from Economic Development Director Nicole Dozier.
Dozier said the architectural and structural engineering contract for the Price Barbershop has been executed and that a pre‑construction site walk took place. She reported "there were some structural concerns that were identified with an existing separation wall due to a significant vertical cracking at the Price Barbershop," and said the design team and architect are evaluating recommendations for stabilization before demolition begins. Staff will continue coordination on outstanding technical items and monitor progress against the project schedule.
Board members thanked staff and the chair said she would stay engaged on project details until the executive director position is filled.
AI generated
The text on this page is AI generated. Summaries, highlights, analysis, and video transcripts are all produced from the original source material.
AI can make mistakes, so if you spot one, and we will fix it for everyone.
Note: the source content is unaltered by us. Any content source we link to, be it a video, an audio recording, or a document, is presented exactly as its publisher released it. That publisher is usually a government body, sometimes an individual official or another organisation.