County staff recommends Blunt Construction for Mount Tabor Park parking and connectivity; lowest bid below estimate
Summary
Staff said 11 bids were opened for Mount Tabor Park connectivity; the low bid from Blunt Construction Company LLC was $379,445.11 and the project will add roughly 35 parking spaces including ADA stalls and trail connectivity, funded by SPLOST in Post 1.
Get email alerts on the Parks Recreation topic
No spam. Unsubscribe anytime.
County staff reported that bids for Mount Tabor Park connectivity and additional parking were opened on July 8 and that 11 bids were received. Staff recommended awarding the contract to Blunt Construction Company LLC at $379,445.11, which came in below the estimated construction cost. The project will construct a parking lot to serve the playground, restroom facility and trails, and includes a staircase and ADA-accessible ramp for direct access to trails.
When asked by a board member how many spaces would be added, staff said the project will provide about 35 parking spaces, including ADA-accessible stalls. Funding for the project will come from SPLOST and the project is located in Post 1. Staff said engineering representatives from Crowell Engineering were present for technical questions.