Colfax council sets pool concrete pour date, approves public update letter

Colfax City Council · June 16, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council outlined a compressed timeline for the municipal pool — concrete pour on July 21 with a 28-day cure — and unanimously authorized a public update letter to explain the schedule and staffing options if the pool can open for limited weekends.

The Colfax City Council on June 16 authorized a public update about the municipal pool’s repair timeline and discussed contingency plans for opening for limited weekends this summer. City Administrator Matt Hammer said the concrete deck pour is scheduled for July 21 and requires a 28-day cure before finishing work and staff-led landscaping.

Hammer described the remaining work sequence: conduit for lights and plumbing will be installed, a liner will be placed after those systems are in, then public works crews will complete landscaping and finish tasks. Mayor Jim Retzer reiterated a pledge that the pool would not remain closed for two years, a commitment he said has guided scheduling decisions.

Council then voted (motion by Councilmember Huntwork, seconded by Councilmember Sevedge) to direct City Clerk Lynda Kramlich to draft a public letter explaining the status and expected timeline; the letter will be published after council approval. Council voted unanimously to approve the letter direction.

The council also discussed recruiting lifeguards from neighboring pools if the project finishes in time to staff limited weekend openings. Details on staffing arrangements and final opening dates will be released in the clerk’s letter after the council reviews the draft.