Council approves up-to-$603,000 amendment for Woodburn Library roof and window work

Woodburn City Council · May 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized an amendment to the Woodburn Library roof replacement contract to cover replacement of failing upper windows and contingency, increasing the award from $548,184 to up to $603,000.

The council authorized a contract amendment on May 11 to expand the Woodburn Library roof replacement project after contractors uncovered failing upper windows during roof removal.

Community Services Director Jesse Cuomo told council the windows are likely original to the building and that replacing the full upper window system — rather than only glass — provides better leak prevention and warranty protection. Council moved, seconded and approved increasing the previously awarded contract with Wood Toppers Inc. from $548,184 to an amount not to exceed $603,000 to cover window-system replacement and contingency.