Board approves $329,640 manhole inflow-reduction contract to restore access after paving

Lake Arrowhead Community Services District Board of Directors · July 1, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board awarded the Manhole Inflow Reduction 2026 Project to Tryco Engineering to raise 186 manholes and 14 cleanouts after road paving; the contract cost is $329,640 plus parts, funded from Wastewater Capital Improvement Fund 210.

Engineering Manager Gus Albarran described the Manhole Inflow Reduction 2026 Project, which will raise 186 manholes and 14 cleanouts to grade after paving to preserve access for maintenance crews. Tryco Engineering submitted the lowest responsive bid; staff said they have used this contractor in prior years with satisfactory results.

Albarran and staff noted the work also qualifies as an inflow-and-infiltration reduction effort under the Consent Decree Order (CDO). The fiscal impact is $329,640 plus additional costs for manhole frames and covers; funding will come from Wastewater Capital Improvement Fund 210. The Board approved the contract and authorized change orders not to exceed 15% of the contract amount.