Board awards Blue Jay groundwater well treatment contract to lowest responsive bidder at $1.547M
Summary
The Board awarded the Blue Jay Groundwater Well Treatment Project to Pyramid Building and Engineering for $1,547,000 and authorized total project authorization including a 15% contingency of approximately $1,779,050 from the Supplemental Water Projects Fund 160.
Get email alerts on the Groundwater Construction topic
No spam. Unsubscribe anytime.
The Board approved awarding the Blue Jay Groundwater Well Treatment Project (Project No. 187) to Pyramid Building and Engineering after receiving six bids; the lowest responsive bid was $1,547,000. Engineering Manager Gus Albarran told the Board the project constructs treatment systems, pumps, and reservoirs necessary to place the previously drilled groundwater well into service and supports the District's goal to reduce reliance on Lake Arrowhead surface water by developing supplemental groundwater supplies. "The lowest responsive bid submitted by Pyramid Building and Engineering in the amount of $1,547,000," Mr. Albarran reported during the meeting.
The total project authorization including a 15% contingency is approximately $1,779,050 and the work will be funded from the Fiscal Year 2026-27 Supplemental Water Projects Fund 160. The Board authorized the General Manager to approve change orders up to 15% if needed and approved the award unanimously.