City to move $89,350 in savings to fund Aldermat Park pathway
Summary
Council approved transferring $89,350 in savings from Helman Park Phase 2 to complete a deteriorated pathway at Aldermat Park, with staff confirming signs and renderings will be posted prior to demolition and construction.
Get email alerts on the Parks And Recreation topic
No spam. Unsubscribe anytime.
The council approved a Parks and Recreation request to transfer $89,350 in savings from the Helman Park Phase 2 project to fund pathway reconstruction at Aldermat Park. City staff reported the Phase 2 contract came in under estimate, leaving savings available to fund needed accessibility and pathway repairs at the neighborhood park.
Mr. Spiller, speaking for Parks and Recreation, said the Phase 2 estimate dropped from $1.6 million to approximately $1.4 million, freeing about $250,000 in savings; he requested $89,350 be reallocated to the Aldermat Park pathway. Spiller said the pathway replacement will improve access to a recently installed inclusive playscape and that signage and renderings will be posted before any demolition. Council members asked for and received confirmation signage would go up ahead of work; the motion to transfer funds carried.