County Weighs Extra $150,000 to Complete Azure Park Court Project After Bids Exceed Budget
Summary
Bids for Azure Park court renovations came in far above budget; staff negotiated the low bid from $421,000 to about $318,000 and asked the board whether to appropriate roughly $150,000 more or pause the project for redesign.
Get email alerts on the Parks Projects topic
No spam. Unsubscribe anytime.
Wythe County staff told the board that the Azure Park court improvement bids exceeded the project's $175,000 budget, with the low bid initially at $421,000 before value engineering reduced it to roughly $318,000. Staff proposed a total project budget of about $325,000 and asked supervisors whether to appropriate an additional $150,000 or call the project back for redesign.
"We've been able to get it down to approximately 318,000," staff said, and requested a modest contingency to allow the project to proceed. Board members discussed usage and whether to refer the matter back to the Buildings & Grounds committee to better quantify expected use and to consider scope changes.
The board did not immediately appropriate the extra funds; members asked staff to explore options, including scaling back some elements, locking existing courts for safety, or returning to committee with usage estimates before authorizing additional appropriations.
Next steps: staff will provide additional usage information and options to the board and, if directed, return the project to the Buildings & Grounds committee for review.