Developer asks for postponement, says turbines are temporary "bridge to grid"
Summary
The applicant asked for an indefinite postponement while it revises proffers, saying the natural‑gas turbine yard is intended as a temporary bridge until Dominion can deliver grid power and that turbines have been ordered with delivery expected in 2027.
Get email alerts on the Developer Rationale topic
No spam. Unsubscribe anytime.
During the public hearing on the Remington rezoning, applicant representative Colin Klitsch asked the commission to postpone action so the company could revise proffers and return quickly. Klitsch said the turbines are ordered and described the plant as a "bridge to grid," adding the company prefers to operate on Dominion power but needs a temporary on‑site solution to resume construction.
Klitsch and staff described a staged Dominion delivery and a CLOA with an anticipated substation delivery around Q2 2030; Klitsch said an initial 30 MW delivery could arrive before the first building is complete and that full substation capacity is delivered in stages. He also asserted the project would bring jobs and tax revenue and emphasized commitments to noise attenuation and safety plans.