Engineer: stormwater system reached capacity during Tropical Storm Debbie; resident mold claim disputed
Summary
District Engineer reported some areas received nearly 8 inches of rain in two to three days during Tropical Storm Debbie, exceeding the road design standard of 5.5 inches in 24 hours; he said the system flowed unobstructed but reached capacity and disputed a resident's assertion that standing water caused mold in one unit.
Get email alerts on the Stormwater Management topic
No spam. Unsubscribe anytime.
District Engineer Charlie Krebs told the Board that MRI’s Pinehurst valley gutter inlet grate replacement is about 80% complete and that he will confirm scheduling for asphalt patching.
Krebs said parts of the community received "almost 8 inches of rain in two or three days" during Tropical Storm Debbie while roads are designed for 5½ inches of rain over 24 hours. He reported that the stormwater system reached capacity but generally flowed unobstructed. A resident said standing water appears to be coming up through a slab and causing mold in their unit; Krebs said he does not believe the standing water is the cause because other units did not report similar issues and noted the developer previously broke a Pinehurst connection when installing a second outfall in 2022. The Board asked Mr. Long to address the item on the next agenda.
Mr. Krebs also proposed that The Club add a drainage connection to lake E1‑A to bypass pipes and inlets during high water events; he will follow up with a schedule and recommendations.